THREAD 4 · FRAUD SCORE: 4/5

Cost Escalation

California High-Speed Rail costs $215 million per mile to build on flat agricultural land. Spain builds comparable high-speed rail for $11-27 million per mile. France: $21-46 million. Italy, on flat terrain similar to the Central Valley: $67 million. Even after accounting for every US-specific cost factor — labor, regulation, environmental review, property acquisition — a 2-4x unexplained premium remains.


The escalation record

YearEstimateScopeEvent
2008$33.6B800 mi, SF-LA by 2020Voters approve Prop 1A
2009$42.6BSameConverted to year-of-expenditure dollars (+27%)
2011$65-98BSameEngineering reality: near-triple
2012$68.4BReduced to "blended"Cut $23B by sharing Caltrain/Metrolink track
2018$77.3BFurther reducedConstruction already behind schedule
2024$89-128B171 mi fundedWidest range ever reported
$33B → $128B
Cost escalation while scope shrank 79%
800 miles promised → 171 miles funded

The 2008-to-2009 jump is telling. Two months after the ARRA application used $33 billion in constant dollars, CHSRA converted to $42.6 billion in year-of-expenditure dollars — a 27% increase. The favorable constant-dollar figure went to voters and the federal government. The real number followed quietly.

International comparison

The most damning evidence is not the raw dollar figure but the comparison to what other countries achieve on similar terrain.

Flat terrain: the apples-to-apples test

ProjectCountryTerrainCost/Mile (2025 USD)Ratio to CAHSR
Madrid-SevilleSpainFlat (Meseta)~$11M1:20
LGV Sud-EstFranceRolling hills~$21M1:10
Recent French avgFranceMixed~$33M1:7
Milan-BolognaItalyFlat (Po Valley)~$67M1:3
CAHSR Central ValleyUSAFlat agricultural~$215M1:1

Italy's Milan-Bologna — the most expensive flat-terrain HSR project in Western Europe — cost roughly one-third of CAHSR per mile. And Milan-Bologna ran through a densely populated corridor, not empty farmland.

What legitimately explains higher US costs

American infrastructure costs more than European for real reasons:

  • Labor: Construction wages 1.5-2x Western Europe, 5-10x China
  • Environmental review: CEQA and NEPA add years and costs
  • Property acquisition: US eminent domain is slow and expensive
  • Prevailing wage requirements: California adds ~20-30% to labor costs
  • Regulatory complexity: FRA, CPUC, and local jurisdiction requirements overlap
  • Litigation: Lawsuits at every stage (Tos I, Tos II, environmental challenges)
  • Buy America provisions: Mandate US-sourced materials at premium prices

Generously, these factors explain a 2-3x premium over Western European costs. They do not explain a 7-10x premium over Spain or a 3x premium over Italy.

The unexplained gap

2-4x
The unexplained premium after adjusting for all US-specific factors
Even generous adjustments leave CAHSR 2-4x higher than comparable Western European projects

The additional premium is attributable to factors within CHSRA's control:

Premature construction. CHSRA rushed construction to meet ARRA deadlines, breaking ground in 2015 when design was only ~15% complete. The State Auditor found this contributed to $600 million in change orders — contractors encountering conditions the incomplete designs hadn't addressed.

Contract explosions. The three construction packages bid at a combined $2.8 billion. They finished at $8.6 billion — a 200% increase through over 1,500 change orders.

The change order machine

Three packages, three stories

PackageOriginal BidFinal CostGrowthChange OrdersContractor
CP1$1.04B$4.05B290%701Tutor Perini (lowest tech score: 68.5%)
CP2-3$1.37B$3.69B170%594Dragados-Flatiron ($1,234,567,890 bid)
CP4$0.45B$0.85B86%289Ferrovial (722km Spanish HSR experience)

CP2-3 merits special attention. Dragados-Flatiron bid exactly $1,234,567,890 — sequential digits — undercutting the next competitor by $506 million, with aggressive "cost-saving" proposals that systematically failed. This is the classic "buy-in/get-well" pattern: bid impossibly low to win, then recover costs through change orders. The 594 change orders and the $537 million settlement (January 2026, largest in project history) followed predictably.

CP1's contractor, Tutor Perini, had the lowest technical score of five bidders (68.5%) but won after CHSRA changed evaluation criteria mid-process to favor the lowest bid over technical competence. The rule change came 65 days after CEO Jeff Morales started — arriving from Parsons Brinckerhoff, the program manager — and reversed a Board-approved two-step selection that would have eliminated the bottom two bidders on technical score. The Board was not notified. Morales's CEO bonus was contractually tied to "getting a bid at or below estimates."

The approval chain

The CHSRA Board delegated unlimited change order authority to the CEO. No dollar cap on amendments to existing contracts — only a $25 million reporting threshold. The CEO could further sub-delegate to staff, who were often themselves consultants.

CHSRA approved amendments "based wholly on the information the contractors reported" with "little documentation demonstrating whether or how the Authority independently evaluated the validity and size of the amendments."

California State Auditor, Report 2018-108|November 2018|Tier 1

The result: CP2-3 grew from $1.37 billion to $3.69 billion through staff-level approvals. The Board learned about the cumulative $2 billion overrun only in March 2023 — after the money was already spent. They were ratifying fait accompli, not authorizing spending.

The electrification anomaly

Either the project faces a massive electrification cost overrun that would add billions to the total, or the budget numbers included in cost estimates and federal applications were not credible. This connects directly to the federal grant fraud case (Thread 3).

The fraud standard

Fraud Standard Assessment
4/5
Material Misrepresentation
$33B→$128B; $215M/mi on flat land vs. $11-67M for international peers; electrification budgeted at 22% of comparable actual costs.
Knowledge
Reason Foundation published $65-81B before the vote. CHSRA converted constant→YOE dollars (+27%) immediately after ARRA application. Premature construction was a known risk.
Intent to Induce Reliance
Low estimates were used to secure voter approval (Prop 1A) and federal grants (ARRA, FSP). Each subsequent business plan revised costs upward after commitments were secured.
Reasonable Reliance
Voters and the FRA relied on CHSRA cost estimates. Federal funds were obligated. Bond debt was incurred.
Damages
The cost escalation itself is documented, but proving damages requires showing that lower estimates were used to induce specific financial commitments — which overlaps with Thread 1 (voter) and Thread 3 (federal). As a standalone thread, the causal chain is harder to isolate.

The defense

The strongest innocent explanation: Every major infrastructure project overruns its initial estimate. Flyvbjerg's research on megaproject cost overruns shows this is a structural phenomenon, not specific to California or this project. The US has uniquely high construction costs due to regulatory requirements, labor markets, and litigation exposure. CHSRA started with an optimistic estimate — as all project proponents do — and reality corrected it. The comparison to Spain and China is apples-to-oranges given radically different labor markets, regulatory environments, and property acquisition processes.

The defense is strongest on the US-vs-international comparison (real cost differences exist) and weakest on the contract management (unlimited CEO change order authority with no independent review is a governance choice, not an inevitability). CP4's relatively controlled performance — same state, same project, same era — suggests the overruns were not inevitable.

What we don't know

Sources

Tier 1 (Primary documents)

Tier 2 (Government reports & research)

Tier 3 (Investigative journalism)

Tier 3.5 (Government-adjacent)

Tier 4 (Analysis)